Your Custom Text Here
JOHN HOLLAND / LEVEL CROSSING
REMOVAL AUTHORITY
Concrete Volume: 9150m3 VicRoads Spec Concrete
Of the 24,600m2, 12,300m2 was placed as blinding in only 5 concrete pours. This was achieved by using a 3D capable laser screed. The remaining 12,300m2 were poured as structural base slabs ranging from 750mm thick to 250mm thick. Base slabs were poured in 11 pours which included the shaping of steep culverts by hand. Speedpro completed works ahead of schedule with no incidents or injuries working 24/7
JOHN HOLLAND / LEVEL CROSSING
REMOVAL AUTHORITY
Concrete Volume: 9150m3 VicRoads Spec Concrete
Of the 24,600m2, 12,300m2 was placed as blinding in only 5 concrete pours. This was achieved by using a 3D capable laser screed. The remaining 12,300m2 were poured as structural base slabs ranging from 750mm thick to 250mm thick. Base slabs were poured in 11 pours which included the shaping of steep culverts by hand. Speedpro completed works ahead of schedule with no incidents or injuries working 24/7
Speedpro Centre Road Level Crossing Removal