Builder: CPB / Lend Lease
Client: Level Crossing Removal Authority
Works completed:
- Unload and install 1,375 precast derailment kerb panels onto the elevated rail corridor;
- Fix approximately 1,150 tonne of reinforcement including electrical continuity welding;
- 15,877 ferrules cast in to bond the rail plinths to the deck;
- 10,227m2 of suspended concrete rail corridor slabs placed and finished;
- 74 Super T diaphragms formed, reinforced and poured;
- 214 Drainage cover plates formed and installed.
Significant time constraints given the nature of the works required Speedpro to multiple work fronts and crews running day and night up to 7 days a week during occupation periods. This challenge was met with a proactive planning approach ensuring Speedpro could meet all productivity requirements and deliver a quality product inside the time allowed
Builder: CPB / Lend Lease
Client: Level Crossing Removal Authority
Works completed:
- Unload and install 1,375 precast derailment kerb panels onto the elevated rail corridor;
- Fix approximately 1,150 tonne of reinforcement including electrical continuity welding;
- 15,877 ferrules cast in to bond the rail plinths to the deck;
- 10,227m2 of suspended concrete rail corridor slabs placed and finished;
- 74 Super T diaphragms formed, reinforced and poured;
- 214 Drainage cover plates formed and installed.
Significant time constraints given the nature of the works required Speedpro to multiple work fronts and crews running day and night up to 7 days a week during occupation periods. This challenge was met with a proactive planning approach ensuring Speedpro could meet all productivity requirements and deliver a quality product inside the time allowed